The
units are in, and installation has begun.
We are getting closer!
|
|
We wondered what was
tearing up the yard, and then we saw it!! A prehistoric Giant
Sloth. |
|
 |
|
 |
|
July 13 - This is where we were
last week.
|
|
The picture shows
tubing going into the “former” boiler room. The 26 1” borings
that go under the church and parking lot have been narrowed into
10 1/4” tubing. We are in the building! |
|
 |
|
 |
|
July 7 -
Boring is completed. They are
making final connections that will go to the unit. Much
of the interior work has been done in the church. We are now
waiting for the units to be delivered. |
|
|
|
|
|
|
|
|
|
 |
|
June 30 - While the rains helped
tremendously the gardens and crops, it is delaying the
geothermal project. They need to dig out the ditches before
hooking up the tubing. They are through with the boring and now
will hook up the tubing into a central location, our former
boiler room. |
|
|
| |
|
|
|
 |
|
 |
|
June
23 - We are just about finished with the boring. This week
they were boring under the KC building, under the parking lot
and
coming up in the grass before the street. They have been doing a
lot of work in the “boiler room.” Our 30 year old boiler has
been removed and the room is being retrofitted for the piping
that will carry cool or hot air to the church and the rectory. |
|
The trench where the piping will be tied together. |
|
|
|
|